Llantwit Major School Ysgol Llanilltud Fawr

New build progress May 2016

PROGRAMME AND PROGRESS

COMPREHENSIVE PHASE 1 SCHOOL COMPLETION

30th March 2017

COMPREHENSIVE PHASE 2 SCHOOL COMPLETION (Demolition & External Works)

19th February 2018

 

CONTRACT DURATION:

124 weeks

CONTRACT COMPLETION:

19th February 2018

CURRENT WEEK:

31

CURRENT POSITION:

On Programme

PREVIOUS POSITION:    

On Programme

 

SECONDARY SCHOOL

Envelope

 Steel Frame is Complete. (revisit for dining hall to allow MEWPS to build above)

 All concrete upper floors are now complete.

 Roofing is 80% complete.

 External Wall SFS and boarding 60% complete.

 Windows have started.

 Fire Intumescent Painting is near completion.

 

Internal works

 Sole plates for partitions have started this week.

 

Services and Externals

 Drainage through the access road to site offices complete.